Underground development in the Valley of the Kings has been progressing, and the first ventilation raise is under development. Detailed mine engineering has been ongoing, and final long lead equipment recommendations have been issued with bids received for a significant portion. Engineering for the transmission line is in the latter stages of completion, with a pole supplier selected and the pole engineering contract awarded. Construction power will be in place for site construction start-up, with bulk earthworks and transmission line construction planned to commence on receipt of permits anticipated this summer.