Milestones to Production

Jul 9. 2018
Second quarter gold production results and provide guidance for the second half of 2018 for the Brucejack Mine. Second Quarter 2018 Production Summary 111,340 ounces of gold produced 14.9 grams per tonne gold mill feed grade 97.7% gold recovery rate 236,990 tonnes of ore milled 2,604 tonnes per day ore milled “With more than 187,000 ounces produced in the first half of 2018, we have delivered on our first half 2018 guidance of 150,000 to 200,000 ounces of gold,” said Pretivm President & CEO Joseph Ovsenek. “The successful integration of our grade control program into our mining process has resulted in increased grade to the mill with production exceeding grade control estimates for the quarter. Brucejack has now achieved steady-state production, and we expect to deliver 200,000 to 220,000 ounces of gold for the second half of 2018.” Second Quarter 2018 Monthly Production   Gold Production (oz) Gold Grade (g/t) Recovery (%) Ore Milled (t) April  35,891 16.6 97.8 73,222 ...
Sep 21. 2017
Ramp-up continues to advance at the high-grade gold Brucejack Mine, and the mine is targeting steady state production for the end of 2017. With the grade ramping up and the mill now exclusively processing stope ore, production of doré and flotation concentrate has increased. As a result of the increased production and the concomitant proceeds from the sale of doré and flotation concentrate, the Company is expected to achieve positive working capital by the end of this quarter. All of the main operating units in the mill building are performing as expected, and the plant is consistently operating at nameplate capacity of 2,700 tonnes per day or better. Optimization of the gold recovery process is ongoing and the start-up issues encountered within the gold room have been addressed. The production of metallic slag has been eliminated. Gold recovery at the shaker table has significantly improved, and overall, gold recoveries are currently exceeding 95%. Long-hole drilling is currently ...
Aug 10. 2017
Construction and mechanical commissioning at the mine has been substantially completed, and the demobilization of construction and contract crews, as well as construction facilities, is nearing completion. The permanent operations team has now assumed full management of the mine, and all of the main operating units in the mill are now fundamentally performing as expected. In May, ore was first introduced to the mill with a focus on ramping up tonnage throughput to nameplate capacity as quickly as possible with low-grade ore. During the month of June, the process plant at Brucejack processed 70,805 tonnes of ore (87.4% of one-twelfth of yearly nameplate capacity) from low-grade ore stockpiles for an average of 2,360 tonnes per day. Under the terms of the credit agreement among the Company and its lenders, the Commercial Production Date is defined as the first day of the calendar month immediately following the first calendar month during which the process plant processes ore at an ...
Jul 3. 2017
Commercial production has been achieved at the Brucejack Mine.   Under the credit agreement among Pretivm and its lenders, the Commercial Production Date is defined as the first day of the calendar month immediately following the first calendar month during which the process plant processes ore at an average rate of 60% of one-twelfth of yearly nameplate capacity (985,500 tonnes per year or 2,700 tonnes per day).  During the month of June, the process plant at Brucejack processed 70,805 tonnes of ore (87.4% of one-twelfth of yearly nameplate capacity) for an average of 2,360 tonnes per day. Higher grade ore has begun to be introduced to the process plant as work continues on optimizing recoveries in the gravity and flotation circuits. For the news release on the construction progress click here ...
Jun 20. 2017
The first gold has been poured at the Brucejack Mine and the flotation and gravity circuits are now operational.  In addition, gold-silver flotation concentrate is being produced and bagged, with initial shipments scheduled.   Construction crews continue to be phased out as construction winds down and the operations team ramps up toward commercial production. For the news release on the first gold pour click here ...
May 1. 2017
Wet commissioning is nearing completion at the Brucejack Mine. The commissioning process was initiated in April and the first ore has been introduced to the process in preparation for production.    Construction of underground infrastructure, including the crusher, rock breaker, feeder, electrical substation, conveying system and transfer towers is substantially complete and commissioned. The conveyor gallery from the Valley of the Kings portal to the mill building has been installed and the conveyor has been commissioned.  Nine hundred tonnes of ore has been introduced as part of the commissioning process and run through the crusher and conveyed to the surge bin in the mill building.  Commissioning of the process plant and service systems is progressing. The variable frequency drives for the SAG and ball mills have been tested and commissioned, with electric motors bumped and drives coupled. Water has been introduced into both mills and water load test operation ...
Mar 31. 2017
The Brucejack Mine transmission line is now energized and dry commissioning is underway.   Wet commissioning remains on schedule to begin in early April with the first ore expected to be introduced to the mill in mid-April. The 57-kilometer long transmission line connecting the Brucejack Mine to the BC Hydro power grid was completed on March 21, 2017 and energized on March 31, 2017 following regulatory approval.  The transmission line will provide low cost, clean energy to power the site including the mill and underground operations. Construction of underground infrastructure, including the crusher, conveyor, and transfer towers is nearing completion and the electrical substation has been energized.  The underground conveying system has been completed with all belts installed.   With the critical mechanical and electrical components in place, remaining roof decking and wall cladding will be completed to enclose the portal building. All conveyor galleries from ...
Mar 9. 2017
Construction of the Brucejack Mine has advanced ahead of schedule and dry commissioning of the mill is now planned for March 2017 with wet commissioning expected in early April 2017. Commissioning was previously planned for mid-2017. Over 144,000 tonnes of ore have been stockpiled on the surface and underground in preparation for mill commissioning. Underground development is well advanced with twelve stopes crosscut on two levels in preparation for long-hole drilling. Cross cutting of another eleven stopes is in progress. A long-hole drill has been mobilized, with long-hole drilling of a test stope underway. All major mechanical and electrical components have been delivered to site and installation and assembly is ongoing. The shell, heads, gears motors and drives for the SAG and Ball mills have been installed and the drives are scheduled to be energized in late March. Electrical and instrumentation along with mechanical and piping installation within the mill building is ongoing. ...
Feb 3. 2017
Construction has advanced ahead of schedule and dry commissioning of the mill is now planned for March with wet commissioning expected in early April. (Commissioning was previously planned for mid-2017.)   Over 110,000 tonnes of ore has been stockpiled on surface and underground in preparation for mill commissioning. Underground development is well advanced with eleven stopes crosscut on two levels in preparation for long-hole drilling and cross cutting of a further four stopes in progress.  Long-hole drills are being mobilized, with long-hole drilling expected to commence the second week of March. All major components have been delivered to site and installation and assembly is ongoing. Process tank installation is 75% complete. The shell and heads for the SAG and Ball mills have been installed.  Electrical and instrumentation along with other mechanical and piping installation within the mill building is ongoing. The 330-person camp which includes mine dry, offices, ...
Dec 15. 2016
Construction and development continues on schedule for commissioning of the underground mine in mid-2017. Following the full enclosure of the mill building in October, internal construction has progressed significantly. Over 45% of the internal structural steel is now complete and concrete continues to be poured and is over 80% complete. Concrete is currently being poured in the gold recovery area and the truck drive through bay. All major equipment continues to be delivered according to schedule including the flotation concentrator which is now on site. Flotation tanks and tailings thickener are being assembled and the process and fire water tanks have been installed. The SAG and ball mills sole plates are now in place and grouted and ready for mill shells installation. SAG mill bearing housings have been installed. Transformers have been installed within the mill. Electrical and mechanical contractors are now on site, and electric and piping installation has been initiated in the ...
Dec 15. 2016
Highlights of the updated Mineral Reserve estimate include: Proven Mineral Reserves in the Valley of the Kings increased to 1.6 million ounces gold (3.3 million tonnes grading 14.5 grams per tonne gold) which is sufficient for the first three years of mine life. Proven and Probable Mineral Reserves in the Valley of the Kings increased to 8.1 million ounces gold (15.6 million tonnes grading 16.1 grams per tonne gold). Areas of gain in the Mineral Reserves are attributed to the following factors: Increasing drill density to 7.5-meter to 10-meter centers allowed for conversion of a significant amount of Probable Reserve to the Proven Reserve category. Mining stopes within the existing Mineral Reserve model along with expansion of the previous Indicated Mineral Resource wire frame accounted for an increase of approximately 620,000 ounces of gold. Several new, adjacent stopes were added to the previous mine plan as a result of the infill drilling reaching beyond the previously defined ore. ...
Oct 27. 2016
Construction at Brucejack has progressed significantly through the summer and fall and a number of key milestones have been achieved. With over 900 contractors and employees the Brucejack Project remains on schedule for commissioning and production in 2017. Mill Facility The structural steel, roof and wall cladding now enclose the mill building. Internal construction is ongoing in preparation of delivery and installation of mechanical equipment. The installation and assembly of the surge bin, the mill substation transformers, the process and fire water tanks and tailings thickener are progressing. Most of the major components including the SAG and ball mills are at site and initial mobilization of the remaining mechanical equipment has begun. 330-Person Camp The three dorms as well as the kitchen facility that make up the permanent camp are in operation and occupied. Transmission Line Construction of the 57 kilometer-long transmission line is reaching completion with all 137 towers ...
Jul 21. 2016
As a result of the 2015/2016 underground infill drill program, the Valley of the Kings Mineral Resource estimate was updated (see news release dated July 21, 2016) . Measured Mineral Resources in the Valley of the Kings increased by 58% to 1.9 million ounces (3.5 million tonnes grading 17.0 grams per tonne gold) and Measured and Indicated Mineral Resources in the Valley of the Kings now total 9.1 million ounces of gold (16.4 million tonnes grading 17.2 grams per tonne gold), an increase from the December 2013 Valley of the Kings Mineral Resource estimate of Measured and Indicated Mineral Resources which totalled 8.7 million ounces of gold (15.3 million tonnes grading 17.6 grams per tonne gold). In summary, the updated Mineral Resource estimate has confirmed the geological model for the Valley of the Kings, and combined Measured and Indicated Resources ‎ have not materially changed. The Valley of the Kings remains open to the east and west along strike, and at depth. ...
Jun 29. 2016
Construction and development at the high-grade gold Brucejack Project continues on schedule for commissioning of the underground mine in mid-2017. Mill Facility Construction of the mill building continues to progress with the pouring of concrete foundations and pedestals for the building as well as footings and pedestals for the surge bin and the SAG and ball mills. Standing of structural steel is underway and full enclosure of the mill building remains on schedule and is expected to be complete in the third quarter. Prior to full enclosure of the building, internal structural steel and mechanical equipment installation will commence. The SAG and ball mills are scheduled to arrive in August. Camp Installation The prefabricated modules for the 330-person camp have been installed and structural interconnection work, electrical installation, communication wiring, and water and sewer piping continue throughout the complex. Steel roof decking is complete for the first dorm and continues on ...
Apr 19. 2016
Construction and development remains on-schedule and on-budget for commissioning of the underground mine in mid-2017. Camp Installation The foundation for the 330-person camp at Brucejack is substantially complete including the installation of structural steel over the cast concrete pedestals. The first prefabricated modules for the camp have been mobilized to site, and installation of services to the camp site is nearing completion. The permanent camp is expected to be operational early in the third quarter of this year. Mill Facility and Portal Excavation Excavation to level the site for the mill facility has been completed, and the concrete contractor has mobilized to site. The concrete and aggregate plants are operational and concrete works have commenced. The structural steel installation for the mill building is scheduled to commence late in the second quarter, with full enclosure of the mill building expected in the third quarter. Installation of internal structural steel and ...
Mar 10. 2016
Construction at the mine remains on schedule for expected commissioning in the third quarter of 2017. The permanent camp pad has been completed with the first concrete poured on January 19, 2016, and mobilization of the 330-person permanent camp to site is expected to begin in March with concrete foundation work scheduled to begin in April. The construction of the transmission line is also expected to commence in April. Bulk earthworks to level the site for the mill building are expected to be completed in March with concrete foundation work scheduled to begin in April. The construction of the transmission line is also expected to commence in April. The pre-production underground development contract was awarded to Cementation Canada Inc., and their crews have been mobilized to site and operating on multiple headings since early January. All long lead-time items have been ordered, including the ball mill, SAG mill, and transformers. Construction power generators are in operation. ...
Feb 17. 2016
On February 17, 2016, we announced an updated cost estimate and project update for the Brucejack Project. Based on the achievement of the 60% engineering milestone, a capital cost estimate was carried out in late 2015 to update the June 2014 Feasibility Study cost estimate for the Brucejack Project. The estimated total project capital cost to complete design, construction, installation and commissioning, including contingencies and working capital, is US$696.8 million. Working capital for the three-month period of post-plant commissioning and initial gold production covers the cost of operations, but does not take into account any revenue generated during this period. The working capital estimate also covers the costs for prepayments related to electrical power and permitting, including US$9 million in government fees and bonds. For the news release on the updated construction cost and working capital estimate click here.   ...
Nov 5. 2015
Basic and detailed engineering activities have been ongoing following completion of the updated National Instrument 43-101-compliant feasibility study for the Brucejack Projectin June 2014. All long lead items have been ordered, including the ball mill, SAG mill, transformers and switch gear. Construction power generators have been delivered to site and commissioned. Detailed project engineering continues along with an evaluation and review of the capital cost budget. Construction at the Brucejack Project commenced on September 5, 2015 following the receipt of all major permits. Activities are focused on bulk earth works, including the pads for the permanent camp and mill building, in preparation for facilities construction in the spring of 2016. Additional construction activities at site have included the excavation of diversion ditches and contact water pond and the widening of the haul road to accommodate construction traffic. The permanent camp has been fabricated offsite and is ...
Sep 15. 2015
The financing package of US$540 million construction financing with the Orion Mine Finance Group and Blackstone Tactical Opportunities has been negotiated. The Financing, which provides for immediate access to US$340 million at closing, will fund a substantial portion of the costs to develop an underground mine at Pretivm’s Brucejack Project. The Financing is comprised of a credit facility for US$350 million, a US$150 million prepayment under a callable gold and silver stream agreement and a private placement of Pretivm common shares for US$40 million.All of the major regulatory permits required to begin development work towards commercial production at the Brucejack Project have been issued. Production Decision The Board of Directors approved a production decision for the Brucejack Project. The production decision was made following receipt of all of the major regulatory permits required to begin development work at the Brucejack Project and the announcement of the financing with ...
Sep 1. 2015
All of the major regulatory permits required to begin development work towards commercial production at the Brucejack Project have been issued. The British Columbia Minister of Energy and Mines has issued a Mines Act Permit approving the mine plan and reclamation program allowing commercial production. The Mines Act Permit allows for the construction of a 2,700 tonnes per day doré and flotation plant, development of an underground mine, and associated facilities and other infrastructure. An Environmental Management Act permit for its Brucejack Project has also been issued by the British Columbia Ministry of Environment which governs effluent discharge during construction and operation. For the news release on the Environmental Management Act and Mines Act Permits click here. ...
Jun 9. 2015
Underground development in the Valley of the Kings has been progressing, and the first ventilation raise is under development. Detailed mine engineering has been ongoing, and final long lead equipment recommendations have been issued with bids received for a significant portion. Engineering for the transmission line is in the latter stages of completion, with a pole supplier selected and the pole engineering contract awarded. Construction power will be in place for site construction start-up, with bulk earthworks and transmission line construction planned to commence on receipt of permits anticipated this summer. For the news release on the progress of the project click here . ...
Apr 2. 2015
Pretivm and the Nisga’a Nation entered into a Cooperation and Benefits Agreement in respect of the Brucejack Project. The Agreement establishes a long-term, mutually-beneficial relationship between Pretivm and the Nisga'a Nation. Under the terms of the Agreement, the Nisga'a Nation will provide ongoing support for the development and operation of Brucejack and Pretivm will honour commitments to the Nisga’a Nation regarding jobs and contracting opportunities at the Project, education and training and financial payments. For the news release on the Cooperation and Benefits Agreement click here . ...
Mar 27. 2015
An Environmental Assessment Certificate for the Brucejack Project by the British Columbia Minister of the Environment and Minister of Energy and Mines has been issued. The Ministers issued the certificate with conditions which have given them the confidence to conclude that the project will be constructed, operated and decommissioned in a way that ensures no significant adverse effects are likely to occur. The environmental review process was led by British Columbia's Environmental Assessment Office ("BCEAO"). The process provides for significant opportunities for Aboriginal groups, government agencies and the public to provide input on the potential for environmental, economic, social, heritage and health effects from a proposed project. Documentation for the BCEAO review process for the Brucejack Project, including the certificate, can be accessed from the BCEAO Project Information Centre (e-PIC) website: http://a100.gov.bc.ca/appsdata/epic/html/deploy/epic_project_home_395.html For ...
Nov 20. 2014
AMEC Americas Limited (AMEC) was awarded the contract to provide the engineering, procurement and construction management (EPCM) services for the Brucejack Project. AMEC is an international engineering and project management firm with recently completed mining projects in British Columbia including New Gold’s New Afton Mine and Thompson Creek Metals’ Mount Milligan mine. AMEC has been involved with the Brucejack Project as a third party reviewer of the June 2014 feasibility study and has participated in constructability and capital cost reviews of the Project. AMEC has commenced detailed engineering and is advancing procurement for surface facilities and underground infrastructure. Flow sheets have been finalized and preparation of general arrangement drawings and procurement packages for long lead items is underway. For the news release on awarding the EPCM contract click here. ...
Jun 19. 2014
The updated Feasibility Study completed for the Brucejack Project confirmed positive economics and outlined an increase in the gold grade. Highlights from the Feasibility Study include: Increase in Mineral Reserve gold grade: Valley of the Kings Proven and Probable Mineral Reserves of 6.9 million ounces of gold (13.6 million tonnes grading 15.7 grams of gold per tonne) West Zone Proven and Probable Mineral Reserves of 0.6 million ounces of gold (2.9 million tonnes grading 6.9 grams of gold per tonne); Gold and silver recoveries of 96.7% and 90.0% over mine life; Mine life of 18 years producing an estimated 7.27 million ounces of gold; Average annual production of 504,000 ounces of gold over the first 8 years and 404,000 ounces of gold over mine life; Estimated project capital cost, including contingencies, of US$746.9 million; Average operating costs of C$163.05/tonne milled over mine life; Base case economics: At US$1,100/ounce gold, US$17/ounce silver and exchange rate of 0.92 ...