Brucejack Reserve Summary

Click here for the Brucejack Resource and Reserve Summary

Mineral Reserve Estimate – April 2019

Valley of the Kings (1,3)

Category Tonnes
(mil)
Gold
(g/t)
Silver
(g/t)
Contained
Gold
(mil oz)
Silver
(mil oz)
Proven 2.0
11.2 11.8 0.7
0.7
Probable 11.1 14.3 10.5 5.1
3.8
Total P&P 13.1 13.8 10.7 5.8
4.5

West Zone (2,3)

Category Tonnes
(mil)
Gold
(g/t)
Silver
(g/t)
Contained
Gold
(mil oz)
Silver
(mil oz)
Proven 1.4 7.2 383 0.3 17.4
Probable 1.5 6.5 181 0.3
8.6
Total P&P 2.9 6.9 279 0.6
26.0

(1)Source: Updated Mineral Reserve Estimate, see news release dated April 03, 2019
(2) Source: Feasibility Study and Technical Report Update on the Brucejack Project, dated June 19, 2014
(3) Base case metals prices of US$1,200/oz gold and US$15.6/oz silver